From beason at jlab.org Wed Oct 8 07:22:10 2025 From: beason at jlab.org (beason at jlab.org) Date: Wed, 8 Oct 2025 07:22:10 -0400 (EDT) Subject: [Utility Outage] Scheduled HVAC Outage - 10/08/2025 07:19 Message-ID: <20251008112210.CBFE99999A@cc-2022.jlab.org> The following HVAC Outage has been Confirmed: Outage: B87 HVAC Outage Proposed By: James Beason Start Time: 10/08/2025 07:19 End Time: 10/08/2025 07:19 Description/Impacts: HVAC outage to support transfer of DDC controls to JCI. Will affect up to 3 days. AHU-1, AHU-2 and HRV will be affected. Minisplits tied to Rooms 101, 104, 105, 107, 108, 111 and 111B may still be in operation. Impacted Areas: Bldg 87: Accelerator Maintenance & Support For more details, visit the webpage listed below: https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=21 From jbeattie at jlab.org Wed Oct 8 08:25:50 2025 From: jbeattie at jlab.org (jbeattie at jlab.org) Date: Wed, 8 Oct 2025 08:25:50 -0400 (EDT) Subject: [Utility Outage] Completed Water Outage - 06/04/2025 09:30 Message-ID: <20251008122550.DBC1B9999A@cc-2022.jlab.org> The following Water Outage has been Completed: Outage: Bldg 87 Backflow rebuild Proposed By: Jeff Beattie Start Time: 06/04/2025 09:30 End Time: 06/04/2025 11:30 Description/Impacts: Will shut down water to building for approx 2hrs to rebuild backflow preventor. All bathrooms and sinks will be out of order while work is being done. Impacted Areas: Bldg 87: Accelerator Maintenance & Support For more details, visit the webpage listed below: https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=7 From beason at jlab.org Mon Oct 20 13:55:37 2025 From: beason at jlab.org (beason at jlab.org) Date: Mon, 20 Oct 2025 13:55:37 -0400 (EDT) Subject: [Utility Outage] Completed HVAC Outage - 10/08/2025 07:19 Message-ID: <20251020175537.2AEF79999A@cc-2022.jlab.org> The following HVAC Outage has been Completed: Outage: B87 HVAC Outage Proposed By: James Beason Start Time: 10/08/2025 07:19 End Time: 10/08/2025 07:19 Description/Impacts: HVAC outage to support transfer of DDC controls to JCI. Will affect up to 3 days. AHU-1, AHU-2 and HRV will be affected. Minisplits tied to Rooms 101, 104, 105, 107, 108, 111 and 111B may still be in operation. Impacted Areas: Bldg 87: Accelerator Maintenance & Support For more details, visit the webpage listed below: https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=21