[Utility Outage] Completed HVAC Outage - 10/08/2025 07:19
beason at jlab.org
beason at jlab.org
Mon Oct 20 13:55:37 EDT 2025
The following HVAC Outage has been Completed:
Outage: B87 HVAC Outage
Proposed By: James Beason
Start Time: 10/08/2025 07:19
End Time: 10/08/2025 07:19
Description/Impacts:
HVAC outage to support transfer of DDC controls to JCI. Will affect up to 3 days. AHU-1, AHU-2 and HRV will be affected. Minisplits tied to Rooms 101, 104, 105, 107, 108, 111 and 111B may still be in operation.
Impacted Areas:
Bldg 87: Accelerator Maintenance & Support
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=21
More information about the Fac_outages
mailing list