Dear Colleagues,
I worry about the second bullet on slide 11…
‘ The emittance values previously provided are not valid and will not be until there is a layout. Beam size will then be recalculated.’
In fact, we have a layout. What is missing to complete the emittance dilution budget are the splitters. We already heave a preliminary emittance budget for the FFA arcs and the new Spr/Rec.
I would refine the statement as:
‘The emittance dilution budget previously provided include contributions from the FFA arcs and the new Spr/Rec, one still needs to include emittance dilution coming from the horizontal splitters as they are being designed. Beam size will then be recalculated.’
Please, let me know if you agree…
Thanks.
Cheers,
Alex
___________________________________
S. Alex Bogacz,
Accelerator Physics Group Leader
Center for Advanced Studies of Accelerators
Jefferson Lab
12000 Jefferson Avenue,<x-apple-data-detectors://8>
Newport News, VA 23606<x-apple-data-detectors://8>
___________________________________
Sent from my iPhone
On Jun 8, 2023, at 4:26 PM, Jay Benesch via FFA_CEBAF_Collab <ffa_cebaf_collab at jlab.org> wrote:
here's the pdf version since powerpoint doesn't play nicely with OpenOffice
<FFA_JULO_2023_Bogacz_Benesch_Brooks.pdf>
_______________________________________________
FFA_CEBAF_Collab mailing list
FFA_CEBAF_Collab at jlab.org
https://mailman.jlab.org/mailman/listinfo/ffa_cebaf_collab
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/ffa_cebaf_collab/attachments/20230608/4aaceb6a/attachment.html>
More information about the FFA_CEBAF_Collab
mailing list