[Halla_parity] HAPPEx III status
Robert Michaels
rom at jlab.org
Fri Aug 21 09:47:18 EDT 2009
>From Mark Dalton below.
E-mail list halla_parity is now a "mailman" list and
there are some glitches which I'm trying to work out.
>
> Dear Collaborators,
>
> The HAPPEx detectors have been installed. Source work to minimise
> helicity correlated beam differences has been completed. The Hall
> has completed the hot checkout and will lock up for first beam
> tonight.
>
> Currently, the major foci for work are on the HRS right dipole, the
> Compton in general and the in situ LED detector linearity
> measurement system. There is also work being done on PREX detector
> tests. We will lock up the hall for physics beam tomorrow (Friday)
> and run optics and pointing measurements over the weekend.
>
> There will be a general target training at 4 pm on Wednesday 26
> August. Those target operators who have shifts before this date
> will be contacted separately to arrange prior training.
>
> Mark
>
>
> --
> Mark Dalton
> Research Associate in Physics
> University of Virginia
> office: +1 757 269 5852
> mobile: +1 757 849 2929
> dalton at jlab.org
> Postal Address:
> 12000 Jefferson Avenue, Suite #4
> Newport News, VA, USA, 23606
More information about the Halla_parity
mailing list