[Halla_parity] PREX status & plans
Robert Michaels
rom at jlab.org
Wed Apr 21 16:26:47 EDT 2010
Tomorrow we'll do beam studies (transv. phase
space in Wien), then at ~2 pm start Moller
commissioning for 10 hours.
Friday morning we'll measure Qsq 8am - 11am.
On Monday we'll do the Wien filter spin flip.
There could also be some Compton beam tuning,
after we improve our diagnostics and have
addressed the HV problems.
Other than that: Production !
https://prex.jlab.org/wiki/index.php/RunPlanDaily
Robert Michaels
Run Coordinator