We are currently in beam permit as MCC is trying to tune beam into the Hall. At present we are the only Hall setup to run - Hall D will lock-up tonight and Hall B tomorrow. If everything goes well we might see CW beam today or tonight. The daily run plans are available from the following wiki page:
https://hallaweb.jlab.org/wiki/index.php/Daily_Run_Plans
After a stable CW beam is estabilshed in the Hall, we will begin our beamline calibrations (BPM, raster etc.).
---
This is a plain text email for clients that cannot display HTML. The full logentry can be found online at https://logbooks.jlab.org/entry/3310126