Here is a brief summary of the meeting this morning:

1) Accelerator still plans to deliver pulsed beam starting Friday afternoon. Hall A lock-up would be noon.

2) Target cool-down has begun. Target operator training will begin during the swing shift today.

3) Both the dipole and quad on Moeller experienced shorts. The quad is fixed and work will begin on the dipole later today.

4) The right arm had a breaker trip last night when Jack tried to power up the dipole. The trip point has been set higher and Jack will try again this morning.