[Halla_running] [Revised Logentry] Hall A status and plans: Friday, November 7
gaskelld at jlab.org
gaskelld at jlab.org
Fri Nov 7 19:15:02 EST 2014
Logentry Text:
--
Hall A is presently in Power Permit to allow final PSS checkout and ARC dipole power supply soak test. Once this is complete, MCC will begin extraction of the Hall A and B beams to the dumplettes, and then begin setup to the Hall.
Upon beam arrival, we will check out the functionality of the raster and check the BPM calibration, etc. After beam-related checkout, we will start to look for LHRS-Calorimeter coincidences.
Detailed run plans for OWL and DAY shift can be found on the Wiki: https://hallaweb.jlab.org/wiki/index.php/Daily_Run_Plans
The left HRS is still being pumped down (it was let up this morning to configure the pins that the new, thick collimator will hang off). Saturday morning (8 am), Jessie Butler will come in to turn on the turbo pumps. Please make sure the MCC is notified that we would like a Controlled Access at this time. If they request a delay, please call me so I can notify Jessie.
Longer term, we plan to take some optics/sieve data in the left HRS - potentially Sunday. Monday morning, we will go to Restricted Access to cool the cryotarget.
---
This is a plain text email for clients that cannot display HTML. The full logentry can be found online at https://logbooks.jlab.org/entry/3304789
-------------- next part --------------
An HTML attachment was scrubbed...
URL: https://mailman.jlab.org/pipermail/halla_running/attachments/20141107/53c3619d/attachment.html
More information about the Halla_running
mailing list