After yesterday's beam studies the accelerator was recovered overnight,
and we're taking data now. There are some beam positions instabilities and
a large compton background, which the MCC experts are now trying to fix -
at the 8 am meeting they seemed to understand what to do.
The plan for today is production data taking.
Tomorrow, day shift, we'll have 3 hours of down due to RF recovery. We
could go into controlled access if necessary, but I have not heard any
requests yet. Please let me know if you have work to do in the hall.
Today we'll have the usual 4 pm RC meeting in the 2nd floor CH meeting
room to discuss status and plans. After that meeting we'll do the
ceremonial hand-off of the RC phone to the next RC, Kijun Park. Good luck
to him !