[Halla_running] [New Logentry] RC update
jbane at jlab.org
jbane at jlab.org
Mon Mar 26 09:40:07 EDT 2018
Logentry Text:
--
RC Update!!
We were able to complete the extra set of high momentum optics on the Ti target during swing shift. We Followed that up by completing bullseye scan, finishing up early owl.
For the last few hours of owl shift and in to day shift MCC had an issue with a vacuum chamber and a vertical separator .
https://logbooks.jlab.org/entry/3548234
https://logbooks.jlab.org/entry/3548190
The plan for MCC today is to investigate the root of the BLM trips. After their investigation on the Beam loss monitors, they hope to give us an opportunistic entry into the hall.
For or entry , we plan to remove the sieve from the left arm, and change the polarity of the LHRS magnet.
We current our experiencing an issue with the raster. Our raster expert has been in contact with MCC and we hope to have the issue addressed soon. And if needed , we can use the hall access to address this further.
---
This is a plain text email for clients that cannot display HTML. The full logentry can be found online at https://logbooks.jlab.org/entry/3548253
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/halla_running/attachments/20180326/779d5d64/attachment.html>
More information about the Halla_running
mailing list