We are current under MCC's Recovery period. They plan to have beam down for ~8 hrs. Rad Con was able to sweep the Hall around 9. We have a few plans for some short term work in the Hall. If anybody needs to access the Hall please let me know.
Summary for last few shifts:
We have had about 26.6 hours of beam on target this weekend(owl -11/10 through owl 11/12), a little less then 50%.
We are moving to the tritium Kinematics and will start taking data on Hydrogen when the beam comes back up.
Reminder:
-Pay attention to the beam stability (BPMs, energy lock/FFB) and raster.
- Check the truck ramp door indicator (orange cone in the camera screen) from time to time
-We are in need of shift workers, please help us out https://misportal.jlab.org/mis/apps/physics/shiftSchedule/index.cfm?expe...
---
This is a plain text email for clients that cannot display HTML. The full logentry can be found online at https://logbooks.jlab.org/entry/3624931
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/halla_running/attachments/20181112/b928dc36/attachment-0001.html>
More information about the Halla_running
mailing list