Hall Status:
The target 15k transfer line was fixed on Monday. Cool down started around 9am this morning.
Hall is still in restricted access for target cool down and magnets check.
Plan:
We are expecting to have the target ready before this swing shift. Then we will ramp up magnets, go through Tritium phase 1,2,3 , and take production data till next Morning.
At 8am Wednesday we will go back to phase 2 for the MCC high current test. Meanwhile we will install sieves slits on both arms to collect optics data. We will go back to production.before noon.
---
This is a plain text email for clients that cannot display HTML. The full logentry can be found online at https://logbooks.jlab.org/entry/3628917
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/halla_running/attachments/20181120/e829a5f2/attachment.html>
More information about the Halla_running
mailing list