Logentry Text:
--
Monday Oct 30th

-Day, Swing and Owl

- we are in restricted access due to commissioning the Hypernucleus Experiment.
- Target was warm up for check the past weeks vaccum/leaks issues
- Several upkeeps of both spectrometers

PLANS FOR TODAY:
- accelerator is under recovery today, mostly all DAY shift.
- we expect to start to cool down the target around noon (just expecting D. Meekins)
- magnets will start to ramp up, as soon we finish with the target
- probably (big if), we will enter in Controlled Access when the target starts to cool down. 
- if everything goes fine (accelerator+hall), we could have beam at SWING shift
- in order to finish the commissioning of the experiment, it is expected several controlled access to the hall along SWING. 

---

This is a plain text email for clients that cannot display HTML.  The full logentry can be found online at https://logbooks.jlab.org/entry/3617646
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/halla_running/attachments/20181030/834bea90/attachment.html>


More information about the Halla_running mailing list