The plan as discussed in the daily run meeting:
Due to the tritium operational procedures, Hall A cannot receive any beam until the target ladder is cold.
The remainder of the plan remains similar:
-Saturday/Sunday - Get target chamber to vacuum
-Monday - Cool target, hope to be ready for beam on swing shift, begin detector checkout (5th pass)
-Tuesday - Finish detector checkout/commissioning, install sieves, run optics data (5th pass)
-Wednesday - (day shift) switch to 2nd pass
HALOG entry:
https://logbooks.jlab.org/entry/3596276
Cheers,
Evan
R. Evan McClellan, PhD
Hall A Postdoctoral Fellow
Jefferson Lab