Good progress has been made on the target recovery. The part where the leak found was taken out this morning and was re-installed after repaired. Target group is working down in the hall, leak checking after the re-installation of the part as well as the Ca target. If everything turns out ok, we expect to lock up the hall sometime during the swing. I will keep you posted on the status, so stay tuned. Current plan is to do Moller polarimeter commissioning once we are ready to get beam back to the hall.
Tomorrow morning, beam studies (to address the beam loss issue, etc) are scheduled at 8 am for 6-8 hours. We will go to the controlled access for the target cool down. if you need to work in the hall, please let RC know and plan accordingly.
---
This is a plain text email for clients that cannot display HTML. The full logentry can be found online at https://logbooks.jlab.org/entry/3696909
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/halla_running/attachments/20190630/f1ef5d86/attachment.html>
More information about the Halla_running
mailing list