Logentry Text:
--

We’re still waiting for signed OSPs to move the spectrometers.  The magnet test group is coming out tomorrow to look at the repairs.  Tomorrow afternoon will have the final walkthrough.  From the time we get the OSP we have about 2 days of equipment moving and 1 day of testing.  Therefore it is likely that we will start taking beam at the end of the week.  The exit beam line was bled up and the target chamber vacuum seems to have held.  Chris Keith will condense the target when the time comes.  SBS 7 is essential so if there are extended delays some other setting will have to be truncated.  Shifts are cancelled until Wednesday morning.



---

This is a plain text email for clients that cannot display HTML.  The full logentry can be found online at https://logbooks.jlab.org/entry/3938940
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/halla_running/attachments/20211108/31dc23cd/attachment.html>


More information about the Halla_running mailing list