[Halla_running] [EXTERNAL] RC Update -- Wednesday 11/24 [resend]

Brad Sawatzky brads at jlab.org
Thu Nov 25 12:09:39 EST 2021


This RC update was sent out Wed afternoon but seems to be stuck in the
sbs_running moderation queue.

The full version (probably with better formatting and working links) can
be found here:
  https://logbooks.jlab.org/entry/3949555

-- Brad (outgoing RC)

========================================================
RC Update -- Wednesday 11/24
========================================================

Lognumber 3949555. Submitted by brads on Wed, 11/24/2021 - 16:22.
Logbooks: 	HALOG
Backlinks: 	Hodo RF status update
Accelerator and Hall Status

    Configuration change to SBS-11 completed during Tuesday DAY shift
        LV cable got pulled out during changeover [1]; fixed, but something to watch/check after next config change
    Accelerator worked on the pass change through Swing into Owl, got some beam into the Hall mid-Owl shift
        Had difficulties completing the Raster and Beam position checkout. Possibly due to optics issues downstream of the raster in the A-line [2], [3]. Under investigation during day shift
        Moller quads had an issue cycling -- now fixed [4]
    DAQ latencies noted on the GEMs seem to be global and caused issues with data taking throughout the night
        It is still unclear why the latency changed [5], [6], but they are being adjusted based on what we are seeing this morning. See more detailed notes in the DAQ sub-detector discussions

    Had some trouble with BBhodo HVs [7]
        Steve suggests a power cycle of the crate may help -- requires escorted access

    Cryo flow to target was found to be constrained last night
        This did not impact the program and was corrected this morning.

    Ran into a few computer related issues during Tuesday swing, now corrected [8], [9]

    4th pass separator issue will be worked on today (Wednesday)
        Original 4th Pass IOT ("IOT3") has been declared unrepairable (for now)
        Plan is to move 2nd Pass IOT up to 4th (then move it back later in the program) [10]
        This primarily impacts Hall C at this point, but there will be downtimes associated with reintegration and tuning once repairs are completed.

Run Plan for Wednesday--Thursday

This will be updated as we better understand what needs to be redone with corrected readout latencies.
We should be able to complete the 'Initial Beam steer-up', raster and beam position checkout this morning.

    The SBS-11 Runplan (PDF) document is on the DocDB. Please update the file there if needed.
    Position + separation of protons and neutrons for SBS11 (Bdl = 1.6 T.m)

 

    [Complete] Beam restoration to the Hall(MCC driven program to get beam to the dump)
        BB Sieve is IN
        Ensure target is OUT
        GEM HVs OFF
        SBS, BB Magnets OFF
        All other systems should be ready to go

 

    After initial steer-up into Hall is complete (call Don Jones if you have issues during Swing/Owl or David Flay during the Day Phone Numbers)
        Verify beam profile with Harp scans
        Determine raster size and positionon target
            When complete be sure to make a halog and update the whiteboard with the new raster and beam position numbers

    Inform the RC when we get here. The plan will be to stop beam to Hall A and allow OPS to work on the 4th-pass line and RF separator system. We will stay in Beam Permit and retake the BBCal cosmics runs (below).

    [Complete] Take BBCal cosmics data with magnets on to get HV settings established when above steering/raster checks are complete. (Call the RC)
        Turn on BB (750A) and ask MCC to ramp SBS to 2100A
        Ensure all detector HVs are ON, set BBCal threshold for Cosmics (~200 Hz), take 500k triggers
        Keep beam out of the Hall until this is completed

 

    Call MCC and ask that they complete their procedure to ramp SBS to production currents (2100A pos) and adjust correctors
        This may require ramping BB to zero (ask them)
        Verify beam position is still where you want it (centered on target)

    Ask MCC will to complete Ion Chamber calibrations on LD2
        'Thin' target ion chamber calibration should be complete Wed OWL (covers carbon foils, dummy)

    Prep for GEM/Optics checkout
        Contact GEM expert (on whiteboard) to support the GEM checkout program
        Contact Holly and Andrew [call numbers on whiteboard] as well, if this starts before midnight
        Turn GEM HV back ON; Ensure other detectors are ready to go.
        Initil threshold settings for BBCAL and HCAL
            BBCAL threshold ~0.5 GeV (readback is: -100 mV)
            HCAL threshold ~0.5 GeV (readback: -80 mV)

    Optics Runs for SBS-11
        Zero Field Alignment
        SBS OFF, BB OFF, Sieve IN
        single C foil target
        BBCAL threshold 0.5 GeV (-100 mV); adjust threshold/beam to get a ~3 kHz of rate
        I = 5 uA
        30 min of beam on target
        Vertex and Angle Reconstruction 1/2
        SBS ON (2100A pos.), BB ON (750A neg.), Sieve IN
        5-foil Optics target
        BBCAL threshold 0.8 GeV (-160 mV)
        I = 20 uA
        60 min of beam on target
        Vertex and Angle Reconstruction 2/2
        SBS ON (2100A pos.), BB ON (750A neg.), Sieve IN
        4-foil Optics target
        BBCAL threshold 0.8 GeV (-160 mV)
        I = 20 uA
        60 min of beam on target

    Escorted Access to take Sieve OUT(needs trained personnel!)
        Call RC ~1 hour before you will need to do this (Brad, Bill, _???_ are authorized to move sieve)

    Low current GEM runs
        SBS ON (2100A pos.), BB ON (750A neg.)
        BBCAL threshold set to establish sufficient rate for a GEM efficiency HV scan; Adjust threshold to get to a few kHz of triggers
        1 uA on LH2 target
        Take 7 ~5 min long runs with different GEM HV settings for quick voltage scan
            GEM expert driven ONLY (ensure GEM expert on shift; or call RC if not sure)
            Voltages: 3653, 3608, 3564, 3519, 3475, 3430, 3385

Confirm Production Threshold Settings in BBCal and HCal

    GEM Rate Study
        Ensure GEM HVs are back at standard settings; detectors should be at Production settings
        SBS ON (2100A pos.), BB ON (750A neg.)
        BBCAL threshold 2.0 GeV (-400 mV) -- want a nominal 100k triggers/run
        LH2 target
        I=1 uA ; take 1 30min run
        I=15 uA ; take 1 30min run
        I=5 uA ; take 1 30min run
        I=1 uA ; take 1 30min run

    Move to Production Running cycle
        SBS ON (2100A pos.), BB ON (750A neg.)
        BBCAL threshold 2.0 GeV (-400 mV)
        HCAL threshold ~0.5 GeV (-80 mV)
        Goal: HCAL calib
            LH2 Target; I = 15uA
            10M triggers (nom. 1 hr)
        Goal: Production
            LD2 Target; I = 8uA
            40M triggers (nom. 4 hr)
        Goal: HCAL calib
            LH2 Target; I = 15uA
            10M triggers (nom. 1 hr)
        Goal: Production
            LD2 Target; I = 8uA
            30M triggers (nom. 3 hr)
        Goal: Production/Dummy
            Dummy Target; I = 15uA
            2.5M triggers (nom. 0.5 hr)

    This nominally takes us to Friday 11/26 in the SBS-11 Runplan (PDF) document. Progress will be reassessed and subsequent runplan updated as needed.

    Upcoming shift schedule issues https://misportal.jlab.org/mis/physics/shiftSchedule/?experimentRunId=GMn-2021
        Several open TO positions starting Nov 26 (Bill H. picked up shifts on 24,25)

Reminders / Notes

    Role sharing between SL and TO was discussed
        TO should support the SL wherever possible while still keeping primary focus on the target
            Beam Time accounting; Shift Checklist tasks are low-hanging fruit
            Suggestion is to have TO start/stop runs and maintain the Run Log spreadsheet?

    Run plan communication / documentation will be 'officially' documented on the Daily_Meetings#RC_Meetingspage
        Don has made the Run Coordinator 'Run Plan / Report' page more visible on the wiki (and nicely formatted it)

Subsystem Updates

    Hall A left side camera not responding (can't switch to it) [11]

    HV Questions/Issues
        BB hodoscope HV issues [12] (Steve, Ralph?)
        HCAL HV status display glitch? [13] -- Cause understood. Due to 'Crate OFF' button being used. Largely cosmetic

    HCal:
        Present data on HCal detector calibrations (timing, energy calibration and uniformity over acceptance, coordinate resolution) at upcoming meeting
        Working on clustering in SBS offline
        Will be using old HVs for SBS-11 startup

    BBCal:
        New HV settings made for upcoming BB/SBS on/off settings
            Contact BBCal experts [Arun] to load these and monitor BBCal performance during beam restart
        Cosmics runs in SBS-11 configuration with magnets on: [14]; significant fringe field gain suppression in PMTs
            HVs adjusted and uploaded [15]
        Parts arrived for PMT dry-air flushing system; needs SSG support

    Timing hodoscope:
        Working on RF alignment
            Rachel gave a status update online and will post to the halog
            Been working through analysis related issues; making progress; several issues remain in presentation
            Mark suggested he may need to write a new class to handle the RF time and make it easier to work with within the analyzer

    Grinch:
        Study of LED data taken under different BB+SBS conditions underway
        Maria/Todd/Bradley will be taking some more opportunistic LED pulser data tonight (Monday)
        Status update on LED data to Halog was requested

    GEMS:
        GEM experts will be monitoring the gas bottles over the holidays (should be fine, but extra eyes will help)
        GEM HV Cosmic Scan Status
            No analysis of these runs yet -- many had bad latency; may not be useful...
        Work continues on calibrating/understanding the new GEM layer
            Andrew reports things seem to be generally working, but some issues still being worked on
            Still investigating the following: large number of fake tracks; possible issues with pedestal suppression, or perhaps indication of cross-talk; unclear... (this hypothesis is still under test)
            GEM "HV-off" cosmics data are on disk -- not clear if it has been looked at (may help disentangle potential cross talk sources)
        DAQ latencies issues noted in the GEMs seem to be global and caused issues with data taking throughout the night
            It is still unclear why these changed [16], [17], but latencies are being adjusted based on what we are seeing this morning: HCAL, GEM, UV GEMs, BBCAL, BBHod, BBGrinch seem to be OK now

    Beamline:
        David F is looking at scaler sanity checks with Paul

    DAQ:
        Need electronics, timing diagrams that represents 'as-built' system
        Latency shift was discovered to be common to entire DAQ
            Seems to have changed around the time the ROLs were updated; which was around the time of some library updates
        Latency configurations seem to be a mess based on comments in Slack (scattered across many files, interactions between global and 'local' settings, etc)
            At minimum, this should probably be documented on the wiki?

    Replay analysis:
        GEM work is ongoing (see above)
        Eric working on end-of-run report file output along with Dave F.
            Would be great to summarize total Charge on target, 'good event' statistics, as well as summarizing efficiencies and other QA related parameters?
            Probably most useful for full replays? (Online histo display should cover most/all of what the shift crew need to monitor already?)
        Online analysis golden runs -- what do shift crew check run-by-run?
            Generate a stripped-down set of plots for shift crew monitoring; experts can use a different Panguin config with a full set of plots?
        Plan for full analyses on Farm?
            This seems to be one of the items holding up more complete analyses of prior data
            Sounds like a plan needs to be hammered out and implemented?


-- 
Brad Sawatzky (he/him), PhD <brads at jlab.org> -<>- Jefferson Lab/ Hall C/C111
Ph: 757-269-5947  -<>-  Fax: 757-269-5235  -<>- Pager: brads-page at jlab.org
The most exciting phrase to hear in science, the one that heralds new
  discoveries, is not "Eureka!" but "That's funny..."   -- Isaac Asimov


More information about the Halla_running mailing list