Hi All,
The hall will be in CANS shortly while the target group works on alignment of the optics. This work should continue into owl on Monday. Survey and alignment will begin afterwards during day shift and BigBite will be moved then. We will take field measurements at kin 3 and begin installation of the target cell Monday day/swing.
We’re on track to bring beam into the hall on Tuesday. I will send an email out shortly to update Monday's shift status for SL and TO. Thanks to everyone who coordinated over the weekend to make accesses seamless and without conflict with scheduled work being done in the hall.
As discussed on Friday, we will NOT meet today for a daily RC meeting. Enjoy your Sunday!
Best,
Sebastian Seeds