After a lengthy discussion, we arrived at the following plan for the next few days:
1) End of the GEn experiment for this running period. It's not feasible to run the reference cell without the carbon hole foils, and we don't know its condition. We don't want to risk rupture of the Be windows.
2) GEn-SBS shifts are CANCELLED through the remainder of this run period. I will also email shift crews. Please spread the word. I hear Hall C is looking for shift-takers.
3) Don has a lengthy (~36hr) plan to do some studies of the systematics for the Moller experiment. If there are any volunteers who would like to come to the counting house to help him (note that this is help for the future MOLLER experiment), please contact Don. The plan will begin sometime this afternoon and continue through Wednesday morning.
4) We plan to open the Hall up for the SAD beginning on Wednesday.
---
This is a plain text email for clients that cannot display HTML. The full logentry can be found online at https://logbooks.jlab.org/entry/4148921
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/halla_running/attachments/20230313/5e233fc2/attachment.html>
More information about the Halla_running
mailing list