Logentry Text:
--
Overall smooth beam delivery.
HV increase on HCal to increase HCal trigger efficiency: https://logbooks.jlab.org/entry/4298852 https://logbooks.jlab.org/entry/4298859 https://logbooks.jlab.org/entry/4298885
Took 2 hrs on LH2 to evaluate the effect of this increase. Improvement of elastic selection while raising threshold to -14 mV: https://logbooks.jlab.org/entry/4299080
One APV had accidentally been removed from the configuration yesterday morning. It was put back in the configuration yesterday evening. https://logbooks.jlab.org/entry/4299090
Short term plan:
* Access tomorrow for GEM, active analyzer, and ECal work;
* Besides the access, continue production data at 10 uA for production on LD2: BBCal threshold at -350 mV and HCal threshold at -14 mV for now. Once per shift, we shall also take 3hours on LH2 at 15uA, same threshold settings.
Accelerator plan remains unchanged so far:
* Hall C pass change + Wien angle change to 0 deg on Thursday (i.e. tomorrow);
* no Wien angle change next Tuesday for Hall A pass change;
* Accelerator beam studies scheduled on May 19th starting at 7am for the rest of the run;
We will have our daily RC meeting on the 2nd floor counting house and via zoom:
Zoom connection link: https://jlab-org.zoomgov.com/j/1616220064
Meeting ID: 161 622 0064
Passcode: 314159
---
This is a plain text email for clients that cannot display HTML. The full logentry can be found online at https://logbooks.jlab.org/entry/4299454
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/halla_running/attachments/20240508/bc1aaad9/attachment.html>
More information about the Halla_running
mailing list