We've been continuing production with 20 uA beam on LH2 target. Yesterday during day shift, taking the opportunity of Hall B pass change, CDET experts made two short accesses to the Hall to fix the CDET DAQ issue, see log entries: https://logbooks.jlab.org/entry/4431691 and https://logbooks.jlab.org/entry/4431702 , after replacing the SD module, the CDET was back online. During OWL shift, we had some small issues to bring up CODA, which was resolved by the DAQ experts. The beam has been stable (we don't have beam until yesterday afternoon due to Hall B pass change, and there was a down time due to thunderstorms during yesterday swing shift), other than that, we've been running smoothly on production.
Charge collected since yesterday's Day to today's owl:
* Total Accumulated Charge at Kin3 so far: 70.88 C (Goal: 100 C)
* Total Accumulated Charge at Kin3 since yesterday : 0.73 C
Shift Summary:
* Yesterday's Day: https://logbooks.jlab.org/entry/4431473
* Yesterday's Swing: https://logbooks.jlab.org/entry/4431732
* Today's Owl: https://logbooks.jlab.org/entry/4432030
RC Meeting:
* We will have RC meeting today at 1 pm in the conference room in the second floor of the CH and on Zoom.
* https://jlab-org.zoomgov.com/j/1616220064
* Meeting ID: 161 622 0064
* Passcode: 314159
Best Regards,
Xinzhan
Hall A RC
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/halla_running/attachments/20250801/f6ca6812/attachment.htm>
More information about the Halla_running
mailing list