[Halla_running] [Revised Logentry] RC Daily Summary 05/08/25

asar at jlab.org asar at jlab.org
Thu May 8 11:40:02 EDT 2025


Logentry Text:
--
Yesterday was the accelerator maintenance day, and after they are trying to recover the beam for all halls. 
  * Late night MCC and Optics Experts tried to set-up beam and could reach Arc 9 by 04:00AM
  * MCC hoping to recover beam to hall A first, by mid day and could send physics beam by Swing shift!!
Hall A: There was access to Hall by GEM, ECal, CDet, Target groups and they accomplished their work by 13:30.
Target: Cryotarget Loop 2 temperature read-back failure, later it was recovered (https://logbooks.jlab.org/entry/4370932 , https://logbooks.jlab.org/entry/4370967) 

There was no plan to access the hall from any subsystem, we requested techs for SBS magnet power box to unlock (https://logbooks.jlab.org/entry/4370955). MCC was request to put hall in power permit. We are still in controlled access.
Shifts summary: 
Day: https://logbooks.jlab.org/entry/4370761
Swing: https://logbooks.jlab.org/entry/4370977
Owl: https://logbooks.jlab.org/entry/4371163
Details of RC summary can be found at: https://sbs.jlab.org/wiki/index.php/RC_meeting_and_Run_Plan,_Thursday,_May_8th

To discuss the updates and the upcoming plan, we will have RC meeting at 1:30 pm today on the second floor of Counting house and via zoom: https://jlab-org.zoomgov.com/j/1616220064
Meeting ID: 161 622 0064
Passcode: 314159


---

This is a plain text email for clients that cannot display HTML.  The full logentry can be found online at https://logbooks.jlab.org/entry/4371405
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/halla_running/attachments/20250508/6f7ffabf/attachment-0001.htm>


More information about the Halla_running mailing list