The Hall was in controlled access this morning to check some remaining
issues. It will lock up around 1 pm. MCC will continue to optimize their
optics and do some stability studies for rest of the Swing and Owl shifts
tonight. We will need shift crew in the counting as planned.
We plan to use a solid target during the day shift tomorrow (Sat) and
being checking out HRS detectors. These checkouts will continue for rest
of the weekend. There is also a plan to go through Compton chicane on
Sunday (Day). We will have regular shifts starting day shift on Saturday
(22nd).