[Hallb-engineering] [Fwd: [Fwd: Proposed Water Outage - 01/23/2010 12:00]]

Doug Tilles tilles at jlab.org
Wed Jan 20 06:38:43 EST 2010


Make up water for the ESR will be put in place, hopefully there will be 
no interruption to the ESR cryo.   Doug



burkert wrote:
>
>
> ------------------------------------------------------------------------
>
> Subject:
> [Fwd: Proposed Water Outage - 01/23/2010 12:00]
> From:
> Mike Syptak <syptak at jlab.org>
> Date:
> Tue, 19 Jan 2010 15:36:36 -0500
> To:
> Kees de Jager <kees at jlab.org>, Volker Burkert <burkert at jlab.org>, 
> Stephen Wood <saw at jlab.org>, "Christopher D. Keith" <ckeith at jlab.org>, 
> "C. Cuevas" <cuevas at jlab.org>, Drew Weisenberger <drew at jlab.org>, Andy 
> Sandorfi <sandorfi at jlab.org>, Graham Heyes <heyes at jlab.org>, Eugene 
> Chudakov <gen at jlab.org>
>
> To:
> Kees de Jager <kees at jlab.org>, Volker Burkert <burkert at jlab.org>, 
> Stephen Wood <saw at jlab.org>, "Christopher D. Keith" <ckeith at jlab.org>, 
> "C. Cuevas" <cuevas at jlab.org>, Drew Weisenberger <drew at jlab.org>, Andy 
> Sandorfi <sandorfi at jlab.org>, Graham Heyes <heyes at jlab.org>, Eugene 
> Chudakov <gen at jlab.org>
>
>
> Hi,
>
> Looks like this affects the end stations and the counting house.
>
> Mike
>
> -------- Original Message --------
> Subject:     Proposed Water Outage - 01/23/2010 12:00
> Date:     Tue, 19 Jan 2010 13:55:46 -0500 (EST)
> From:     Ron Bartek <bartek at jlab.org>
>
>
>
> The following Water Outage has been Proposed:
>
> Outage:      4KW ESR Water Main Valve Installation
> Proposed By: Ron Bartek
> Start Time:  01/23/2010 12:00
> End Time:    01/23/2010 18:00
> Description: Must install water main isolation valve to support 4KW 
> ESR project schedule
>
> For more details, visit the webpage listed below:
> https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=1
>
>
>





More information about the Hallb-engineering mailing list