I have moved the crane inspection up an hour during which time we will move the Clean Power transformer. So we will be installing the last Pcal as soon as the inspection is done. Guy's we will need to finish the installation on Tuesday so we can move to the as found Alignment on Wed. We will then begin to install the FTOF supports, and cable trays. Eugene when will the cable trays be in?