To: "Rebecca Yasky" <ryasky at jlab.org>, "Lyn Wells" <wellsl at jlab.org>, "Mark Wiseman" <wiseman at jlab.org>, "Stephanie Vermeire" <schatzel at jlab.org>, "Jonathan Trexler" <jtrexler at jlab.org>, "Sherry Thomas" <sthomas at jlab.org>, "Eric Sun" <qsun at jlab.org>, "Gina Shackelford" <gina at jlab.org>, "Patrizia Rossi" <rossi at jlab.org>, "Sally Fisk" <fisk at jlab.org>, "MeLaina Evans" <melaina at jlab.org>, "Kaydee Moore" <daviskay at jlab.org>, "Dennis Miner" <miner at jlab.org>, "Christopher Miller" <cmiller at jlab.org>, "Bob May" <may at jlab.org>, "Fulvia Pilat" <pilat at jlab.org>, "Bert Manzlak" <manzlak at jlab.org>, "Dave Mack" <mack at jlab.org>, "Bob Legg" <rlegg at jlab.org>, "Kelly Krug" <krug at jlab.org>, "Sherri Kopczynski" <sherri at jlab.org>, "Kim Kindrew" <kindrew at jlab.org>, "Phillip Kessler" <pkessler at jlab.org>, "Kathleen Jones" <kojones at jlab.org>, "Ryan Johnson" <johnsonr at jlab.org>, "Valerie James" <vjames at jlab.org>, "Samika Hawkins" <shawkins at jlab.org>, "Randy Hartman" <hartman at jlab.org>, "Joe Preble" <preble at jlab.org>, "Joanna Griffin" <jkoro at jlab.org>, "Javier Gomez" <gomez at jlab.org>, "Probir Ghoshal" <ghoshal at jlab.org>, "Christine Fragapane" <chummel at jlab.org>, "Rolf Ent" <ent at jlab.org>, "David Chopard" <dchopard at jlab.org>, "Greg Adams" <gadams at jlab.org>, "Mike Spata" <spata at jlab.org>, "Michael Bevins" <mbevins at jlab.org>, "Mary Logue" <logue at jlab.org>, "Latifa Elouadrhiri" <latifa at jlab.org>, "Howard Fenker" <hcf at jlab.org>, "Eugene Chudakov" <gen at jlab.org>, "Mitchell Laney" <laney at jlab.org>, "Lynn McKnight" <mcknight at jlab.org>, "Claus Rode" <rode at jlab.org>, "Allison Lung" <lung at jlab.org>, "Paul Collins" <paulc at jlab.org>, "Paul Brindza" <brindza at jlab.org>, "Steve Lassiter" <lassiter at jlab.org>, "Jonathan Creel" <creel at jlab.org>, "Michelle Lechman" <lechman at jlab.org>, "Renuka Rajput-Ghoshal" <renuka at jlab.org>, "Dave Kashy" <kashy at jlab.org>, "Glenn Young" <gyoung at jlab.org>, "William Merz" <merz at jlab.org>, "Dana Arenius" <arenius at jlab.org>, "John Hogan" <hogan at jlab.org>, "Leigh Harwood" <harwood at jlab.org>
Cc: "Michael Dallas" <mdallas at jlab.org>, "Bob McKeown" <bmck at jlab.org>, "Hugh E. Montgomery" <mont at jlab.org>
Sent: Saturday, May 11, 2013 2:06:52 PM
Subject: 12 GeV Upgrade and Lehman Review
Dear All,
The past 6 months and more have been quite tough for the 12 GeV Upgrade Project. Developing a new baseline while maintaining progress on the project itself was a considerable strain and the uncertainties significantly raised the pressure and the tension.
In such circumstances, eventual success is even sweeter than usual.
The outcome of the Lehman Review was a clear recommendation to proceed to rebaselining, along with appropriate concern that we maintain and enhance our efforts to bring in the suite of superconducting magnets. What was also very pleasing was the expression of support we received from the Office of Nuclear Physics.
This success depended on a large fraction of the lab staff, and if we take into account the work that is going on in the halls, and in the accelerator where installation is the name of the game, the list of addressees is manifestly inadequate. Nevertheless, let me congratulate you and thank you for all you did to make this campaign as successful as it was.
Mont
PS. Feel free to forward this note to anyone you think should have received it.