Dear all,
Attached is what we discussed regarding the work list below.
We will have bi-weekly meetings to track the progress and
to define new items necessary for preparation to the fall run.
Thanks, Stepan
On 5/27/14 2:28 PM, Stepan Stepanyan wrote:
> Dear all,
>
> We will have a meeting tomorrow from 3:30pm to 4:30pm in f228
> to discuss several urgent items for running beam in Hall-B in few
> months. Meeting is on your calendar. Items to discuss are:
> A Counting room furniture
> B Restore Hall-B upstream beamline monitoring and controls
> C Restore FC vacuum and signal readout
> D Finalize beamline drawings, location of beamline elements
> E Restore IOCs (two in forward carriage will be located in
> pie-tower)
> F Cables from the hall to the counting room (patch panel on
> south side of the space frame)
> G Cables from pie-tower and north side of the space to the south
> patch panel
>
> Regards, Stepan
>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: Punch list.pdf
Type: application/pdf
Size: 63312 bytes
Desc: not available
URL: <https://mailman.jlab.org/pipermail/hallb-engineering/attachments/20140529/0cc98b9d/attachment-0002.pdf>
More information about the Hallb-engineering
mailing list