Logentry Text:
--
There were two events that effected our solenoid.
1) the Hall A Q2 tripped and ramped down at 22:53 
This caused a large flow increase in the warm return line and thus temporary pressure increase.
The solenoid lead flow bumped but it recovered.

2) The Hall C TARGET started to warm 

It looked like it went down first then went up. This may or may not have effected the Solenoid.
At present all looks OK to continue the run




---