[Hallb-engineering] Power Outages

Denny Insley dinsley at jlab.org
Fri Feb 5 17:10:31 EST 2021


Thanks Krister

________________________________
From: Krister Bruhwel <bruhwel at jlab.org>
Sent: Friday, February 5, 2021 5:08 PM
To: Denny Insley <dinsley at jlab.org>; Hallb-eng <Hallb-engineering at jlab.org>
Cc: Todd Kujawa <kujawa at jlab.org>
Subject: Re: Power Outages

Hello,

I'll look it up as best as I can.

Thanks,
Krister
________________________________
From: Denny Insley <dinsley at jlab.org>
Sent: Friday, February 5, 2021 2:56 PM
To: Krister Bruhwel <bruhwel at jlab.org>; Hallb-eng <Hallb-engineering at jlab.org>
Cc: Todd Kujawa <kujawa at jlab.org>
Subject: Re: Power Outages

Good afternoon Krister,

    First off thanks for the update. Secondly, would you please give us a quick run down of what's on these panel schedules. It would help to know exactly what is going to be effected so we can plan accordingly.  I may be a little gun shy after the last week but better safe than sorry.

Thanks,
Denny


________________________________
From: Hallb-engineering <hallb-engineering-bounces at jlab.org> on behalf of Krister Bruhwel <bruhwel at jlab.org>
Sent: Friday, February 5, 2021 2:49 PM
To: Hallb-eng <Hallb-engineering at jlab.org>
Cc: Todd Kujawa <kujawa at jlab.org>
Subject: [Hallb-engineering] Power Outages

Hello,

In support of the RICH air compressors and Raster power supplies installs the following panels will go down in about a week from now:

ESB - for about 2-3 hours
BUPH2 - for about two separate 2 hour outages
BUPL2 - for about 1-2 work shifts

Please let me know if there are any problems or concerns.  Once I have more exact dates on the panel outages, I will send another email.

Thanks,
Krister
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/hallb-engineering/attachments/20210205/30ea9ff5/attachment.html>


More information about the Hallb-engineering mailing list