[Hallb-engineering] [New Logentry] Follow-up Re: Follow-up Re: Follow-up Re: Follow-up Re: HallB torus burp

kashy at jlab.org kashy at jlab.org
Thu Aug 24 10:35:02 EDT 2023


Logentry Text:
--
The procedure for the first half of the burp has been fully updated, except for adding the plots which I have yet to be able to reliably create and move from computer to computer!
The procedure calls out cooldown can start when the vacuum at TC8103 reaches ~1E-3 torr and presently it is 1.15E-3 torr. But because the blower inlet valve did not open when it should have this needs trouble shooting.
I'm going to request that the DSG have a look at the hardware and software and work with the Hall B team to diagnose this issue.

Otherwise the burp while a bit painful on the vacuum side was successful. We should not wait over 2 years to perform this operation again. 18 months should be the max.



---

This is a plain text email for clients that cannot display HTML.  The full logentry can be found online at https://logbooks.jlab.org/entry/4170256
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/hallb-engineering/attachments/20230824/a52a34bd/attachment.html>


More information about the Hallb-engineering mailing list