[Hallb-engineering] [New Logentry] Hall B dewar disconnect and 4K circuit purification check and cleanup

Probir Ghoshal ghoshal at jlab.org
Thu Jan 9 21:37:00 EST 2025


Thanks to all helping with cool down moving forward.
This is the best opportunity to learn. I hope we don’t have to this again.
Thanks Dave, Sandesh and Hall B engineering team.
Regards
Probir
________________________________
From: Hallb-engineering <hallb-engineering-bounces at jlab.org> on behalf of kashy--- via Hallb-engineering <hallb-engineering at jlab.org>
Sent: Thursday, January 9, 2025 4:40 PM
To: esr-users at jlab.org <esr-users at jlab.org>; hallb-engineering at jlab.org <hallb-engineering at jlab.org>
Subject: [Hallb-engineering] [New Logentry] Hall B dewar disconnect and 4K circuit purification check and cleanup

Hall B dewar disconnect and 4K circuit purification check and cleanup<https://logbooks.jlab.org/entry/4325556>

Lognumber 4325556<https://logbooks.jlab.org/entry/4325556>. Submitted by kashy<https://logbooks.jlab.org/user/kashy> on Thu, 01/09/2025 - 16:36<https://logbooks.jlab.org/entries?start_date=1736455000&end_date=1736462200&book=HBLOG&book=HBTORUS&book=CLOG>.

Logbooks:       HBLOG<https://logbooks.jlab.org/book/hblog> HBTORUS<https://logbooks.jlab.org/book/hbtorus> CLOG<https://logbooks.jlab.org/book/clog>
Entry Makers:   kashy, dinsley, gopinath

The Hall B dewar was disconnected from the DBX per ePAS 5741 rev1

The next step in getting ready for cooldown is to check to see if any significant contamination exists in the 4K supply circuit.

Flow to check contamination per phase 1 sketch was established at 13:50, 13minutes later the contamination level at the purifiers (CCT10N21R) peaked at 2.9ppm and recovered back to baseline of 1.3pppm approximately 30minutes later.

We will proceed to go to phase 2 which will allow flowing thru the rest of the circuit overnight by
1) lower the amount of flow through the Dewar supply bayonet (a manual valve in Hall B)
2) Closing 4K supply valves in the magnets
3) Adding flow through both 4K supply valves backward toward ESR by flowing 300K 4atm gas from the CD circuit PV8563W in the DBX through the PV8566T to PV8512T and through PV8566S to PV8512S

By morning we should have a fully warmed and clean 4K supply circuit.
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/hallb-engineering/attachments/20250110/821c5bfe/attachment.html>


More information about the Hallb-engineering mailing list