Logentry Text:
--
Purification will continue over the weekend.
At present we are not able to flow more than 0.46g/s the restriction is partailly because of the small valve at ESR and could also be some plugging in the tranferline to/from ESR. If we could flow more then we would warm faster, but at present there is no way to change the plumbing in ESR.
---
This is a plain text email for clients that cannot display HTML. The full logentry can be found online at https://logbooks.jlab.org/entry/4325766