[Hallb-engineering] [New Logentry] Hall B TL Status
kashy at jlab.org
kashy at jlab.org
Mon Jan 20 07:05:01 EST 2025
Logentry Text:
--
Hall B TL 4K supply circuit was fully warmed. 51F minimum temperature was recorded 1/16/25. No significant contamination was recorded even though the circuit went sub-atmospheric ~6 times during the SAD (SAM). 2024.
Cooldown of the TL and piping in the Torus and Solenoid starting now using LN2 cooled helium.
The plan for tomorrow 1/21, is that Cryo will be installing the 4K supply U-tube and 4K cooldown will commence.
---