[Hallb] shift cancellations
    Nathan Baltzell 
    baltzell at jlab.org
       
    Mon Aug 21 12:11:40 EDT 2023
    
    
  
Dear All,
*** The first shifts for RG-D will now be Monday, September 11, day shift.  All prior shifts are cancelled. ***
Current estimates have the accelerator ready for physics on the 5th, starting with beam delivery to C, followed by D, but the new Hall B cryotarget may not be fully ready until the 15th.  Since shifts on the week of the 11th are assigned to locals, we'll keep them active for now.
Regards,
Nathan, PDL
    
    