[Hallb] RG-D shift schedule

Nathan Baltzell baltzell at jlab.org
Thu Jul 20 10:21:45 EDT 2023


Hello Everyone,

Additional delay is now official.  First shifts will now be September 1, and all prior shifts are cancelled.

The delay is expected to be accounted for by an extension in the spring, and the shift schedule has been updated accordingly, through May 5.

*** As a first round, for those institutions whose shifts have been cancelled, we'd like to ask if you can pickup shifts in the extension.  If so, please contact Bryan. ***

Regards,
Nathan (PDL) and Bryan


> On Jun 29, 2023, at 1:22 PM, Nathan Baltzell <baltzell at jlab.org> wrote:
> 
> Hello Everyone,
> 
> More delays to the accelerator schedule are materializing, related to longer than expected procedures in preparation for 2K cooldown.
> 
> It sounds like there will surely be no beam for physics before September.
> 
> But, as there's no official schedule changes yet, the best guidance at the moment is to not book travel arrangements for shifts before September.
> 
> Regards,
> Nathan, PDL