[Hallb] RG-E shifts update

Nathan Baltzell baltzell at jlab.org
Sun Mar 17 13:23:57 EDT 2024


Dear All,

The accelerator is recovering from vacuum issues;  no beam before day shift tomorrow.

*** Tonight's shifts are cancelled.   Tomorrow's day shift is on standby. ***

-Nathan, PDL

________________________________________
From: Nathan Baltzell
Sent: Friday, March 15, 2024 2:18 PM
To: clas_members at jlab.org; hallb at jlab.org
Subject: RG-E shifts update

Dear Everyone,

Startup for RG-E is slightly delayed.  Final upstream beamline assembly is in progress, to be followed by pump down, and then survey tomorrow morning before closing the hall.

**** First shifts will start tomorrow, Saturday, March 16, at noon 12:00. ****

-Nathan, PDL