[Hallc_running] CHANGE: Sweep starts at 4:15
Howard Fenker (m)
hcf at jlab.org
Sun Dec 17 11:08:04 EST 2017
Sweep of Hall C starts at 4:15 or so.
Regards,
Howard
> On Dec 17, 2017, at 10:49 AM, Howard Fenker <hcf at jlab.org> wrote:
>
> All-
>
> The plan at the moment is to start a sweep of Hall C at 3pm today (Sunday).
> If you need to do any work in the hall before 1-pass beam starts during
> swing shift today, plan to have it finished prior to 3pm.
>
> We will take 1-pass beam for HMS optics, etc., until Monday day shift.
> The SHMS dipole checkout will take place on Monday.
> As soon as the SHMS is certified as ready, we will resume its optics
> studies with 1-pass beam.
> Target filling is tentatively planned for Tuesday morning.
>
> Howard
> Hall-C Run Coordinator