We have completed the first kinematic point at Q2=3.0 W=2.32 x=0.40 with all three SHMS angles.
Accelerator was at about 40% efficient for Monday
At about 9:30 today switched to Q2=2.115 W=2.95 x=0.21 theta_Shms=13.74
Need 10hrs LH2 and 1hr dummy for each SHMS angle. That is roughly one day per point
assuming 40% efficiency. So we should be able to change out the aerogel on Friday.
I also asked the the 7A harp be looked at during that downtime.
To keep track of commissioning tasks and physics status,
I made a wiki status page at : https://hallcweb.jlab.org/wiki/index.php/Kaon_LT_Status_Page
We will meet this afternoon at 4:30pm in the second floor counting house:
https://hallcweb.jlab.org/wiki/index.php/RC_daily_meetings_and_daily_run
---
This is a plain text email for clients that cannot display HTML. The full logentry can be found online at https://logbooks.jlab.org/entry/3602746
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/hallc_running/attachments/20181002/4b0c7e35/attachment.html>
More information about the Hallc_running
mailing list