Logentry Text:
--
>From the MCC meeting this morning:
--> Both linacs will be pumped down on Monday (Sep/17)
--> Hall C is coming up first and the expected lock down time is by the end of the day-shift next Thursday (4pm, Sep/20th).
Hall C update:
--> All systems remain shut.
--> The HMS and SHMS motors were installed yesterday, but not electrically connected.
--> Shifts are canceled until 8am, Sep/20th (Next Thursday).
--> We will have a RC meeting at 4:15pm.
--> Howard has Argon flowing through the SHMS and HMS drift chambers (DCs): **DO NOT** operate the SHMS and HMS DCs
https://logbooks.jlab.org/entry/3594225
https://logbooks.jlab.org/entry/3594240
https://logbooks.jlab.org/entry/3594241
---
This is a plain text email for clients that cannot display HTML. The full logentry can be found online at https://logbooks.jlab.org/entry/3594397
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/hallc_running/attachments/20180913/b50510a2/attachment.html>
More information about the Hallc_running
mailing list