[Hallc_running] [New Logentry] RC Daily Update
jones at jlab.org
jones at jlab.org
Sun Sep 30 10:15:01 EDT 2018
Logentry Text:
--
Around midnight the accelerator stopped beam for injector work. https://logbooks.jlab.org/entry/3601137
My understanding is that the energy spread in the South Linac became too large to deliver beam to any of the halls.
The injector work was done through owl. At present an injector expert is still at the lab and they
are working to get the injector and rest of machine into a state to deliver between 20-40uA to Hall C.
Then Monday they will come up with a plan to improve the machine to get higher current to Hall C.
We have nearly finished the elastic singles data. Have to finished the Al dummy at the last setting.
Then we can move on to the elastic coincidence.
Since we are still in the commissioning phase, we will meet this afternoon at 4:30pm
in the second floor counting house: https://hallcweb.jlab.org/wiki/index.php/RC_daily_meetings_and_daily_run
It would be good to review the status of the commissioning analysis.
1) BCM calibration
2) HMS Optics and Central momentum
3) SHMS Optics and Central momentum
Since we are still in the commissioning phase, we will meet this afternoon at 4:30pm
in the second floor counting house: https://hallcweb.jlab.org/wiki/index.php/RC_daily_meetings_and_daily_run
4) Buffered vs Unbuffered data comparison.
5) Elastic SIMC comparison.
---
This is a plain text email for clients that cannot display HTML. The full logentry can be found online at https://logbooks.jlab.org/entry/3601191
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/hallc_running/attachments/20180930/4c2f16ba/attachment.html>
More information about the Hallc_running
mailing list