Thermal cycling of 1L07 is complete and seems to have been beneficial.
The open question is still 1L20. It should complete the 'warm up' side of the cycle this afternoon, then they will begin to cool it back down. We should know if the gradient issue on that module is resolved Sat/Sun.
I would like to plan for a 'status update' RC meeting in A110 following the Hall C meeting on Monday (3:30pm or so).
---