Hello all,
           Additional two weeks has been added to the Hall C shift schedule to compensate for
the downtime from power outage on Mon July 1st from which the machine did not recover until
Wednesday owl (July 10th) . Even at that point, the machine could not deliver
above 15 uA and beam time was lost for most of Thursday for retuning the machine.
          Depending on the machine uptime, the VCS experiment would start on Wed (July 17th).
The Hall C summer running would now end on Monday Aug 5th.

      You can sign up for shifts at
https://misportal.jlab.org/mis/apps/physics/shiftSchedule/index.cfm?experimentRunId=HALLC-SPRING-2019

CHeers,
              Mark