Spotty beam with significant downtimes last night, but some progress was made. Pion-rates seem to be about 50% of what was expected, but there are some questions about the pion-yield script. Experts are digging into it -- if we're lucky, we are undercounting.
Q2=0.375, W=2.20 is complete
Q2=0.425, W=2.20 is in progress.
As of now, we have 3--4 beam-hours of data taking to go before we will take a controlled access to move the SHMS out to a larger angle. The expectation is that this will happen late-day shift, early-swing.
After that we must complete the 3-pass run plan and move to 4-pass. The earliest the 4-pass change could happen at this point is Sunday.
Still on the todo-list for 3-pass:
- H elastic singles: p=-2,3, -1,96, -1.85
- heep check coin run
- Arc energy measurement (TBD?)
---
This is a plain text email for clients that cannot display HTML. The full logentry can be found online at https://logbooks.jlab.org/entry/3695971
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/hallc_running/attachments/20190628/112e3469/attachment.html>
More information about the Hallc_running
mailing list