[Hallc_running] [New Logentry] RC Update
latif at jlab.org
latif at jlab.org
Sun Mar 17 17:00:07 EDT 2019
Logentry Text:
--
- The CSV experiment successfully finished the data taking by 3:30 PM.
- All magnets have been set to zero currents.
- The SHMS has been rotated to 20 deg and HMS to 40 deg.
- The targets are parked now.
- The hall is fully surveyed and in controlled access.
- Detector and beam pipe installation will take place starting from tomorrow.
- Shifts are canceled till Tuesday day shift. Shift takers on Tuesday Swing shift are on standby and should check e-mail prior to coming to the counting-house.
---
This is a plain text email for clients that cannot display HTML. The full logentry can be found online at https://logbooks.jlab.org/entry/3669226