[Hallc_running] [EXTERNAL] Re: [New Logentry] RC update (Sept 12) -- NO RC meeting today

Brad Sawatzky brads at jlab.org
Sat Sep 12 23:04:34 EDT 2020


It seems the Hall C access on Monday will start at 10am as planned.

** Watch for confirmation on Sunday, however. **

-- Brad

On Sat, 12 Sep 2020, Brad Sawatzky wrote:

> Dave G. and I will be taking an opportunistic access at 4:15pm today to try
> to address the iochc10 issue.
> 
> We will cancel the 4:15pm meeting today.  There will be a meeting tomorrow
> (Sunday)
> 
> NOTE: I was recently notified by the PD that the Hall C controlled access on
> Monday may shift to 2pm instead of 10am.
> 
> ----------------------------------------------------------------------------
> 
> Saturday 12 Sept 2020.
> 
>                               General updates
> 
> (See [8]d2n Run Plan 2020 for broader status/overview.)
> 
>   o Presently down from 2pm (until 5--6pm) for an RF klystron replacement
>     [[9]https://logbooks.jlab.org/entry/3846701]
>   o Production running on Transverse target (@ 90); Kin-C, Kin-Z continues.
> 
>        o General plan when this is done is to complete Kin-A, Kin-X
>          (partially done already); then move on to Kin-B/Y and/or 1-pass
>          running as time allows.
> 
>   o Moller measurement was rescheduled for today (2nd attempt); still
>     working on it as of 3:30pm (Accelerator issues) [10][1]
>   o Should move to Kin-A, Kin-X in the next day or so and finish 90-deg
>     running there
>   o Target should be rotated to 270 deg on Monday
>   o Max Target Tommy polarization @ 90 since yesterday has been 38.5%
>     [11][2], it seems to have plateaued at 378% today [12][3], [13][4]
> 
>        o For comparison, maximum seen with target at 90 deg last week was
>          44% (9/5/2020 22:56:38)
>        o FWIW, that is similar to the maximum seen at 270 was 37.5% [14][5];
>          Recent max around 36% (Thursday) [15][6]
> 
>   o Moller measurement completed Friday 86.1% [16][7], (incl. 0.9%
>     bleedthrough correction from Hall A)
>   o Significant down during Friday swing due to problem with iochc10 IOC
>     which handles Moller controls, magnet cryo, etc
> 
>        o Found to be in boot, crash, reboot loop [17][8], hardware and
>          software investigations (including Software On-Call) ultimlately
>          unsuccessful [18][9]. System went down again in Owl [19][10]
>        o Next step is likely swapping out the VME crate; talking to Jack for
>          some support.
>        o Brad will install some cameras to at least monitor the cryo
>          situation at the next opportunity
> 
>   o Once the Hall came out of Controlled Access in early swing beam has been
>     pretty good
> 
>   o Junhao reports the spectrum analyzer parts are ready to go for Monday
> 
>        o RadCon has been looped in and will support
> 
> Notes for the Future
> 
>   o Beam Studies planned for Monday@ 10am to 6pm (including recovery), Sept
>     15
> 
>        o RadCon will support going to CA at 10am, we can stay in CA for
>          roughly 2 hours; OPS wants Hall C dump available after that
>        o Simona wants access at this time for SOLID cherenkov related work
>        o Target work
> 
>             o Install spectrum analyzer collimator
>             o Check field at target region for 270 setting, if possible
>             o Want to determine field direction at the precision of a few
>               degrees vs the alignment laser
> 
>        o Bill, Murchhana check compass/field measurements and will report
>          back at Sat RC meeting
> 
>   o [20]1-pass runningtentatively scheduled for Sept 17/18
> 
>        o Hall A would like a specific date soon so they can finalize their
>          end-of-run plans
> 
> Pending Issues
> 
>   o Check EPR calibrations (particularly for 270deg setting, but others too)
>     [Melanie]
>   o Magnet EPICS PV timeout issue; may have to reboot skylla10 on Monday?
> 
>        o Some Magnets Channels Lost Connection Briefly [21][11] (Saturday,
>          2pm)
>        o Also had to add more error checking to the angle reporting in the
>          CODA run-start GUI last week too (same softIOC as above)
>        o 'Heartbeat' issue reported by Steve Lassiter last week
> 
>   o Target polarization for Tommy @ 270 is low (mid to high 30s)
> 
>        o Spectrum analyzer collimator was broken at some point and present
>          optics setup may be allowing transient light to interfere with
>          spectrum measurement and QWP scans
>        o JP wonders if the field direction is off for the transverse
>          settings (Bill, Murchhana: see note in Target group chat from late
>          Thursday)
> 
>   o Beam energy drifts
> 
>        o Hall C 5-pass polarization goes down as energy (HALLC:p) goes up
>          [22][12]
> 
> Opportunistic Jobs/Access
> 
>   o Beam Studies planned for Monday, Sept 14 (Note date change!)
> 
>     Target calibrations / tests
> 
>        o Just before Moller measurement, and/or other known downtimes
>        o See [23]D2n_Run_Plan_2020#Target_Calibrations_and_Tests
> 
>                               Current Run Plan
> 
> Saturday DAY -> Saturday SWING
> 
>   o Continue production data (HMS Kin-C/SHMS Kin-Z) with pol 3He target,
>     Transverse/90 polarization with NMR every 5 hrs.
>   o [TBD] Move to Kin-A, Kin-X and continue Transverse/90 running there?
> 
> Saturday OWL -> Sunday DAY
> 
>   o Continue production data with pol 3He target, Transverse/90 polarization
>     with NMR every 5 hrs.
> 
> References
> 
>    Visible links
>    1. https://logbooks.jlab.org/entry/3846729
>    2. https://logbooks.jlab.org/entry/3846729/edit?destination=email/send
>    3. https://logbooks.jlab.org/entry/3846729/delete?destination=email/send
>    4. https://logbooks.jlab.org/entry/3846729
>    5. https://logbooks.jlab.org/user/brads
>    6. https://logbooks.jlab.org/entries?start_date=1599937386&end_date=1599944586&book=HCLOG
>    7. https://logbooks.jlab.org/book/hclog
>    8. D2n Run Plan 2020
> 	https://hallcweb.jlab.org/wiki/index.php/D2n_Run_Plan_2020
>    9. https://logbooks.jlab.org/entry/3846701]
>   10. https://logbooks.jlab.org/entry/3846082
>   11. https://logbooks.jlab.org/entry/3845852
>   12. https://logbooks.jlab.org/entry/3846692
>   13. https://logbooks.jlab.org/entry/3846581
>   14. https://logbooks.jlab.org/entry/3844366
>   15. https://logbooks.jlab.org/entry/3845243
>   16. https://logbooks.jlab.org/entry/3846252
>   17. https://logbooks.jlab.org/entry/3846242
>   18. https://logbooks.jlab.org/entry/3846365
>   19. https://logbooks.jlab.org/entry/3846525
>   20. D2n Run Plan 2020
> 	https://hallcweb.jlab.org/wiki/index.php/D2n_Run_Plan_2020#1-pass_Running
>   21. https://logbooks.jlab.org/entry/3846677
>   22. https://logbooks.jlab.org/entry/3844493
>   23. D2n Run Plan 2020
> 	https://hallcweb.jlab.org/wiki/index.php/D2n_Run_Plan_2020#Target_Calibrations_and_Tests


-- 
Brad Sawatzky, PhD <brads at jlab.org>  -<>-  Jefferson Lab / Hall C / C111
Ph: 757-269-5947  -<>-  Fax: 757-269-5235  -<>- Pager: brads-page at jlab.org