The accelerator restored beam to Hall C around 00:00 today. The owl crew did the harp scans and carbon hole check, and beam size and position looked surprisingly good. Significant production on LH2 resumed around 02:00 . 

As of 08:22, the run sheets showed a running total of 4008 pi+. The day shift crew will take some Dummy target data today. 

We will have an RC meeting tomorrow/Friday at 10am. 

Bluejeans link: https://bluejeans.com/861439920
RC meeting page (under construction): https://hallcweb.jlab.org/wiki/index.php/RC_Meeting,_Friday,_October_22_,_2021


---

This is a plain text email for clients that cannot display HTML.  The full logentry can be found online at https://logbooks.jlab.org/entry/3929669
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/hallc_running/attachments/20211021/b13f8703/attachment.html>


More information about the Hallc_running mailing list