[Hallc_running] [Revised Logentry] RC Summary 28 - 29 October
narbe at jlab.org
narbe at jlab.org
Sat Oct 29 08:15:02 EDT 2022
Logentry Text:
--
No beam during Oct 28 due to ongoing repair work for 1L18, involving transformer repair.
During this time, Bob Michaels, Dave Abbott, and Brian Moffitt made some progress on the DAQ crash issue for SHMS. They have a work-around for the TO shift takers
https://logbooks.jlab.org/entry/4071950
Beam was restored around 00:40 on Oct 29. Been taking data since then on a host of targets.
Beam position check was done with the Carbon target
https://logbooks.jlab.org/entry/4072193
Present settings are
SHMS: P = +1.63, Theta = 10 (GeV, degrees)
HMS: P = +9.2, Theta = 35
As of now, the plan is to continue with data taking until Monday when stable 60.0uA beam might be attainable while Hall A changes to 3-pass.
There won't be a RC meeting today. Contact the RC for any changes to plan.
- Your RC (Narbe)
---
This is a plain text email for clients that cannot display HTML. The full logentry can be found online at https://logbooks.jlab.org/entry/4072455
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/hallc_running/attachments/20221029/913fbf67/attachment.html>
More information about the Hallc_running
mailing list