[Hallc_running] [New Logentry] RC daily summary
ssanties at jlab.org
ssanties at jlab.org
Tue Feb 14 10:55:02 EST 2023
Logentry Text:
--
After recovering the beam last night at almost 10 pm, we ran very stable overnight at 40 ua. We have collected 54K/72K on 3He for the first cycle in this kinematic. Therefore, if the beam
cooperates, we will change targets today.
Yesterday, Dave Meekins filled the cell: https://logbooks.jlab.org/entry/4130917
In the hall we have had no major issues. We only had dipole interlocked yesterday in the swing shift but we were able to recover it rapidly, and all while the south linac had the cryo issues. https://logbooks.jlab.org/entry/4130500
Yesterday, Casey noted that when the target position was updated, the encoder position was changed. The autoDB script was not updated, so the standard kinematics files did not have the target mass entered correctly. He fixed the issue yesterday: https://logbooks.jlab.org/entry/4130895
People doing analysis: please take a note of the runs that have that issue.
Accelerator: The plan is to deliver beam to all halls, therefore there are not any plan in the following week for any kind of study, unless something dramatically changes.
The only plan on the white board to our Hall is the target change next Monday-Tuesday. Those days there are many activities happening in the hall, please plan accordingly and let the RC know.
A big thanks for all the people helping us to fill the shifts, especially the students who are breaking records taking shifts (30+ and 40+ numbers). We literally couldn’t run without you, Thanks!
---
This is a plain text email for clients that cannot display HTML. The full logentry can be found online at https://logbooks.jlab.org/entry/4130973
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/hallc_running/attachments/20230214/49c5935d/attachment.html>
More information about the Hallc_running
mailing list