[Hallc_running] [New Logentry] RC Report - 02/13/2024
voutier at jlab.org
voutier at jlab.org
Tue Feb 13 10:35:01 EST 2024
Logentry Text:
--
RC Report - 02/12/2024
--------------------------------
It has been an excellent data taking period with no issues to report but only improvements.
ABU 86% - BNA 12% - PCC 2% - UED 0%
HMS Camera : the camera is back on-line, thanks Dave.
NPS NDX; radiation monitors readback is alive again. Ellen/Sue investigated the issue and did something, probably an IOC reboot.
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
Tomorrow is maintenance day from 6am to 8pm. Hall C will be in controlled access by 9:30am.
RadCon is informed and the priority for surveys is: Accelerator, Hall C, Hall B which take us up to 9:30am.
Known accesses are :
i) - NPS work team (5 persons at the same time)
ii) - Safety Walkthrough (3 persons)
iii) - Spectrometer support group (Heidi/Lars +1 person)
iv) - 22 GeV LDRD investigations (Dave + 4 persons)
Tentative schedule
09:30am - 03:30pm i)
09:30am - 11:00am ii)
11:00am - 01:00pm iii)
01:30am - 03:30pm iv)
-------------------------------------------------------------
NPS pre-work checklist for Wednesday 2/14
-------------------------------------------------------------
1) Description of work
Replacement of the front multiplexer connecting to the front temperature sensors.
2) Involved individuals
JLab: Joe Beaufait, Aaron Brown, Larry Carraway, Dave Gaskell, Jerry Nines
NPS: Joshua Craft, Mitchell Kerver (or other NPS students)
3) Tools required
o 2.5 mm hex driver (Josh)
o Replacement Multiplexor/connector (in Hall C counting house)
4) Course of actions
o Ask MCC to move Hall C in controlled access as soon as possible after the beam is taken away (Crew on shift)
o Ask for switching-off the sweeper magnet (Crew on shift)
o Lock the sweeper magnet out (Dave, Joe)
o Turn off NPS HVs (Josh, Mitch)
o Move the calorimeter to 6m (Jerry, Josh, Larry, Mitch)
o Open the calorimeter box, replace the multiplexor/connector (Aaron, Josh, Mitch)
o Move the calorimeter box back to 4m (Jerry, Josh, Larry, Mitch)
o Unlock the sweeper magnet out (Dave, Joe)
o Turn on NPS HVs (Joe, Mitch)
5) Schedule
MCC is currently planning to stop beam delivery at 6am. The Hall C is expected to be in controlled access at 9:30am. Beam delivery to halls should be established for 8pm.
Link to 11:00 RC meeting
https://jlab-org.zoomgov.com/j/1617015555?pwd=L09IQ216dml6ZmM5ODExVjFsMX
Meeting ID: 161 701 5555
Passcode: 288953
---
This is a plain text email for clients that cannot display HTML. The full logentry can be found online at https://logbooks.jlab.org/entry/4251798
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/hallc_running/attachments/20240213/7bb4bd6a/attachment.html>
More information about the Hallc_running
mailing list