[Hallc_running] [Revised Logentry] RC Daily Update 04/28/2025
jpoudel at jlab.org
jpoudel at jlab.org
Mon Apr 28 13:50:02 EDT 2025
Logentry Text:
--
We got an update from Paul Powers after opening up the junction box that there is some mess to clean up and also need additional work on drainage and sealing. This is estimated to take till tomorrow to finish up. We also learnt that breakers for the transformer need to be replaced, which they have already ordered. We will hear more updates tomorrow morning.
I talked with RadCon and Jerry (work Coordinator) to install the guard rails to access the GEMs. I see the guard rails are already installed when I was in the hall in this afternoon.
As we are down, there will be No RC meeting today, instead LAD group will focus on discussing the data analysis.
---
This is a plain text email for clients that cannot display HTML. The full logentry can be found online at https://logbooks.jlab.org/entry/4366895
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/hallc_running/attachments/20250428/2b7ac107/attachment-0001.htm>
More information about the Hallc_running
mailing list